Client: Allegheny County Airport Authority

Project Name: Landside Parking Lot Rehabilitation

Project Timeline: April 2021 – April 2022

Construction Amount: $944,444

Services Provided: Construction Management & Construction Inspection (CM/CI)

Project Overview:

This project includes three phases of work: The first phase of work was the landside parking lot, which encompassed approximately 2 acres of pavement removal, demolition, and replacement in addition to pavement underdrain and work on stormwater inlets. The second phase of work is at the Central Service Bay and consists of concrete and asphalt repair and replacement in the adjacent parking lots and concrete replacement at the Central Services Bay loading dock. The loading dock work includes replacement of the horizontal surface as well as drainage other ancillary work.

Project Role:

SB Thomas & Associates provided CM/CI services for ACAA on this project including cost estimating and constructability reviews during design, conducting the pre-bid and site visit, fielding bidder questions and preparing the bid addendum, conducting the pre-construction meeting, and providing daily on-site inspections throughout construction. We have staffed this project with a Resident Construction Manager (RCM) who is responsible to oversee one on-site inspector and conducts all job meetings, manages submittals and RFI, prepares pay estimates, and other functions. The Inspector will conduct daily on-site inspections, complete daily inspection reports, provide photo documentation, calculate actual quantities of work completed, monitor the contractor’s progress among other functions.